SETTING UP FOUNDATIONS

Innovation – Nordsee-Windpark Global Tech I – North Sea

From October 2012 to April 2013, Lars Haaber Andersen was present on the powerfull vessel Innovation as a Marine Warranty Surveyor. The jack-up vessel was built in 2012 and is 161,37 meters long.

Lars successfully supervised the installation of several wind turbine foundations in the North Sea. Among main tasks one could mention: foundation load-outs, foundation installations and heavy lifting supervision.

The Offshore Windparks Global Tech 1, situated 100 kilometers off the German coast, consists of 80 wind turbines of 5-megawatt class (type AREVA Wind M5000-116) and was completed in August 2014.

(Picture: MarineTraffic.com)